The development of Rue Montrochet, managed by SPL Lyon Confluence, is being carried out in several stages to adapt to the delivery schedule of the surrounding housing blocks:
- this summer, 2023: definitive development of the road and of the north pavement on the east and west sides of the street, and construction of the south pavement (from Cours Charlemagne to Quai Perrache);
- summer 2024: definitive development of the central part of Rue Montrochet (between Chemin des Ecoliers and Rue Smith), once all of the buildings of the Albizzia project have been completed.
The work being carried out:
- creating the south pavement
- creating a two-way bike path (to be opened in 2024)
- creating a plant bed all along the street (east of Cours Charlemagne)
- installing lamp posts
- developing the roadway
This project is being completed in conjunction with work being carried out on the networks.
This may cause occasional traffic disruptions in the area. We apologise for any undue inconvenience, and we will try to minimise the level of disruption as much as possible. Thank you for your understanding.
Nearby, the roadworks begun on Rue Smith in spring 2023 should be completed by mid-July > find out more
This project is part of the broader development of public spaces in the Marché neighbourhood, managed by SPL Lyon Confluence on behalf of Métropole de Lyon and the City of Lyon > find out more