The works to make Quai Perrache a two-way street were undertaken in coordination with both government and Métropole de Lyon departments. They included extending the slip road for the M7 exit towards the Pasteur intersection, by installing additional reinforced concrete barriers during the nights of 3 and 4 August 2023.
It also involves:
- preparatory works, which began in early July:
o construction of a 4 m footpath on the east part of Quai Perrache,
o development of networks,
o installation of traffic lights and creation of a pedestrian crossing at the Perrache/Eynard intersection,
- Modification of the traffic plan from 4 August, with the following streets becoming one-way: Eynard (West > East), Nivière-Chol (East > West) and Vuillerme (North > South),
- Creation of two cycle paths: Nivière-Chol (West > East) and Vuillerme (South > North).
Making Quai Perrache a two-way street is a 3-month experiment that should make it possible to assess the conditions for implementing this development in the Champ neighbourhood.