The development works, coordinated by SPL Lyon Confluence, are scheduled to last 12 months, broken down into several phases:
- March 2026: preparatory works and relocation of water and electricity networks,
- from April onwards:
- earthworks and laying of utility networks,
- creation of the concrete structure for the future skate park;
- from this summer onwards:
- creation of access points, paths, surfacing, edging, and green and terrace spaces,
- installation of urban furniture (benches, lighting, fountain);
- winter 2026-2027: planting of 320 trees and seedlings;
- spring 2027: works completed.
The main consequences of these works include:
- closure of the work site (access maintained for barge residents and emergency vehicles),
- reorganisation of pedestrian traffic at the Pasteur intersection.
- Vehicles will still be able to access the slip road.
This site is currently neglected and is set to become a new public space available to anyone who wishes to have fun, eat next to the water or simply take the time to see the city from a new perspective. It will also be a new biodiversity reserve in the heart of the city, creating a connection between Gerland Park and the banks of the Saône. Designed in three sections, the Jardin du Rhône will include:
- a course for urban activities and skating (the skate ribbon),
- a planted area on the banks of the river,
- a terrace for a boat restaurant or other business (a call for projects will be launched by Voies Navigables de France),
- a protected natural area, where visitors will be able to observe the biodiversity of the banks of Rhône without disturbing the animals (beavers, etc.).