Champ

A GIANT PLAYGROUND TO BE DELIVERED IN SUMMER 2024

Development of Le Champ began in 2018 with the creation of La Station Mue, its park and Le Petit Champ (delivered in 2021) located south of H7, and continued in spring 2023 with the opening of ZadigaCité and the launch of the summer season of La Station Mue in April. In autumn 2023, a new, highly symbolic step was launched by SPL Lyon Confluence: the start of work on the future Allée Canopée (formerly “Transversale”) and a large playground, called “Le Caterpilou”. Delivery (phase 1) scheduled for summer 2024! Opening : 3rd of July 2024.
Information

Practical information

Caterpilou is open every day from 10 a.m. to 8 p.m. except days of strong winds and/or storms.
Address: 155 cours Charlemagne, Lyon.

EN BREF

  • Delivery date:
    • Phase 1 (Playground) : summer 2024
    • Phase 2 (Allée Canopée): summer 2025
  • Contributing parties:
    • SPL Lyon Confluence (Contracting Authority) 
    • BASE (Project Management, Landscaping Contractor)
    • OGI Lyon (Project Management, Engineering/SCMC)
    • ON (Project Management, Lighting Designer)
    • EODD (Project Management, Sustainable Development & Biodiversity)
    • Greenstyle (Roads & Utility Services, Green Spaces)
    • Bouygues Energie Services (Lighting)
    • Sols Confluence (Concrete Ground Coverings) 
    • Teridéal Segex (Fountains)
    • SMC2, Plein Bois, Technopieux (Structure, Playground)
    • SP2SE (Health & Safety Coordinator)
  • Surface area(s): 
    • 1 200 m2 (playground)
    • 12 000 m2 (Allée Canopée)

PARTICULARITIES

WORK IN TWO STAGES

Development is planned to take place in two phases.

  1. From July 2023 until summer 2024, work will focus on developing Allée Canopée and building the play structure, especially visible since early 2024. During this period, the site will be inaccessible to the public, with certain exceptions, until the playground opens to the public in summer 2024.
  2. At the end of 2024, a second construction phase will begin. This will involve developing the surrounding area and the future forecourt of the former Halle Caoutchouc, set to become a place dedicated to health in the city.

A GIANT PLAYGROUND FOR ALL LYON CITIZENS

With the aim of energising Le Champ in the same way as La Station Mue has managed to do, the playground, named "Caterpilou" due to its caterpillar shape, will be both a destination for the people of Greater Lyon and their families looking for exceptional and fun play equipment in green surroundings, and a public space for local residents, professionals and stakeholders to take a break and unwind.

A LARGE CANOPIED WALKWAY TO CREATE A COOL SPOT IN THE CITY

Connected to the playground, the former Transversale from the Herzog & de Meuron project has become the Allée Canopée in the BASE project: 200 trees, 1,000 m2 of canopy and 33% of surfaces depaved for maximum comfort, even in summer, i.e. three times more than the initial project! Seating furniture will help to cool down the walkway, which gives pedestrians and active forms of mobility plenty of space and promotes community encounters.

COOL PUBLIC SPACES

Near the playground, misting arches will provide welcome coolness on hot days. Public toilets will be available.

On the Allée Canopée, fountains (drinking fountain and a triangular fountain to dip your feet) will allow people to cool down.

Locate

Information

Practical information

! As part of the completion of the development of the Caterpilou and the Canopée alley, the playground and its park will be closed from December 2 to 20, 2024 and then from January 6 to 31, 2025 due to planting work requiring multiple machines.
From December 21, 2024 to January 5, 2025, the Caterpilou will be open every day from 10 a.m. to 8 p.m.