Enlarge the image
Ouvrons Perrache phase 1, le chantier d'extension du tram T2 © Jérôme Boucherat (juin 2020)

Construction

Tram line T1/T2: night-time works

So as not to interfere with the smooth running of the tram and traffic, construction works will take place at night along Cours Charlemagne, between rue Casimir Perrier and Passage Panama. Some noise disturbance will be unavoidable, and more noticeable in the quiet of the night!

Published on

Profiles: User

Provisional schedule :

  • from Monday 28 September to Friday 2 October, 10:00pm-5:00am : demolition of Tram T1’s concrete platform and cutting of the rails,
  • from 5 to 6 October, 8:00pm-5:00am : installation of two temporary railroad points on the tram platform. TCL network disruption: from 8:00pm, Tram T1 will serve stations from IUT Feyssine to Perrache. Replacement buses will run between Perrache and Debourg,
  • from 6 October to 23 November : the T1 tram line will run in two separate parts, from IUT Feyssine to Hôtel de Région- “Patinoire”, and from Hôtel de Région-Montrochet to Debourg.

 

Find out more :

  • about travel on public transport: TCL on +33 (0)4 26 10 12 12 and on the website  tcl.fr